Parc Champigny, Repentigny, 2013

Landscape Architect : Karyne architecte paysagiste ( KAP )
Landscape Architect : Karyne architecte paysagiste ( KAP )
Landscape Architect : Karyne architecte paysagiste ( KAP )

Slideshow

Project description

Parc Champigny had not received any upgrade since 1970 and our client, the City of Repentigny, decided it was time to bring about several improvements. The two-year project began in 2012. A pool was built as was a new centre at the heart of the park to accommodate as many users as possible. In addition, citizens can now use the wading pool, soccer field, ballpark and four tennis courts. To have something for everybody, green spaces, trails and playgrounds were also replaced or upgraded. The landscaping work includes 3,445 square feet of Bolduc Citadin Modular Anthracite Pavers.

Products used

For more information on the product, click on the icon.

Project location

Orders and inquiries

E-mail : info@bolduc.ca

Phone : 418 387-2634

Toll free number : 1 800 463-8966